Project
Covering Temporary Wall with Shrink Wrap
In this project, an existing wall was fitted with a temporary wall that would remain unprotected for an extended period. Without measures, the wall could be exposed to rain, snow, wind, and UV radiation for months, with a high risk of
Challenge
- Moisture and dirt that would penetrate through the temporary wall.
- Risk of discoloration and damage from UV during a long construction period.
- Risk of concrete water seepage during adjacent works.
- Project in an environment where additional fire safety was required.
Our Approach
Our team tightly wrapped the entire temporary wall with professional shrink wrap. We chose NVO (non-flame sustaining) film, ensuring the facade was not only protected against weather conditions but also met safety standards for public spaces.
- The film was applied on-site and carefully tensioned.
- All seams and connections were sealed airtight.
- Thanks to the shrink technology, the wall received a tight and durable covering that lasts at least one year.
Result
- The wall remains completely dry and protected throughout the construction phase.
- No risk of seeping concrete water or rain.
- A fire-safe solution that meets the client’s requirements.
- The facade also looks neatly finished, which is important for construction sites in public view.